Iraq – Port Umm Qasr 2003

 
 

Project

Deepening of the southern port of Umm Qasr

Location : Iraq
Client :
Contractor :
J.V. Great Lakes –Dredging International
Period : 2003

 

Scope of work

Capital Dredging

     

General Information

In order to make the supplies to the country going and to rebuild its society and economy, a safe and accessible port is of vital importance.

 

Description of the works

Over the past months, the self-propelled cutter suction dredger “Aquarius” has carried out important deepening works in the southern port of Umm Qasr.

No doubt Umm Qasr offers a “peculiar” working environment.
There was, for instance, the permanent presence of American and British troops and rolling stock and there were the extreme temperatures and the risks of stumbling on live ammunition.
The large amounts of scrap in the access channel, made it necessary to clean the cutter head every fifteen minutes. Therefore we welded grids in the cutter head. After that we were able to dredge for three to four hours in succession.

The continuous concern for the safety of people and equipment and a whole series of safety measures helped the joint venture to bring this urgent assignment to a satisfactory conclusion.

 

Main Equipment

Cutter suction dredger AQUARIUS